Denver Water Construction Project

Denver Water Pipeline Construction – Staging Update

Denver Water Update

September 11, 2020

The snow on Tuesday has had a slight impact on SJ Louis’s restoration schedule and they were unable to complete the seeding over the weekend as planned. They are waiting for the ground to dry out, which should be soon, and will then seed the area. It is my understanding they were hoping to have the fencing complete this week.

read more

Denver Water Pipeline Construction Schedule – March-May

Denver Water Pipeline - May 29 Construction Update

The new on-site Project Manager has communicated that they are continuing to work on the dirt piles, hoping to have most of it removed so crews can start cleaning up by the first week in June.

The on-site Project Manager stated his priority is to move out of the Trails HOA space as quickly as possible. Reclaiming will begin after the first week in June, so crews will still be visible and in our space.

read more

Denver Water Pipeline Construction – March 2020 Update

March Update on Denver Water Project

There will be construction equipment working around the pump house off 60th that will spill over to our HOA open space.  The ground will be regraded and seeded upon completion.

This part of the project is scheduled in the next 2 weeks.

read more

Denver Water Pipeline Construction – February 2020 Update

February Update on Denver Water Project

There will be construction equipment working around the pump house off 60th in the next 2 weeks. Staging of equipment should remain on Denver Water property.

The current schedule is for the pipe to be laid in Trails open space by July, 2020 due to several schedule delays.

read more

Denver Water Pipeline Construction – September Update

September Update on Denver Water Project

The project manager confirmed that The Trails section of the project is still on a December/ January time line.

  • Work is on-going and continue around the pump station on Denver Water property.
  • In October there "may" be staging of pipe in addition to removing of top soil in The Trails open space.
  • The project manager will contact us in the event of any planned activity on our property.
  • Lucas Menebroker has been invited to the November meeting to update us on The Trails/Denver Water project and answer our questions.

read more

Denver Water Pipeline Construction – Update

Update on Denver Water Project

The Trails HOA Board met the Contractor Neighborhood representative and the Denver water representative to discuss construction involving The Trails HOA land.

  • The time frame for The Trails HOA construction is currently set for Dec. 2019 - January 2020.
  • It was agreed that staging of construction materials will be moved as far away from our houses in the very SE corner of our property off Easley and South of the creek.
  • Further updates in late 2019

Click the button below to view a PDF of the details for the staging area.

read more